TACTICS OF INFRASTRUCTURE PROJECTS
?How we Work
?Where we work
?Vision and Mission
?Members Area
?Sanitation Problems
?Impact of our work
?The need

Selection of Project Area

? Visual survey.
? Mapping of the area.
? Existing infrastructure documentation.
? Situation analysis.
? External linkages - WASA / FDA planning NOC.

Community Mobilisation

? Selection of community activist.
? Short listing of influential peoples - mutual under standing regarding problems.
? Individual meetings for need assessment.
? Conceptual clarity of development process & motivation.
? Organisation of lane committee.
? Selection of lane manager among lane committee.
? MoU between lane committee & ASB.

Project Implementation

? Level survey design & cost estimation.
? Resource mobilisation - money collection by lane committee.
? Purchase of material, labour arrangements and money management by lane committee.
? Start of physical implementation.
? Technical supervision by ASB.
? On site training & technology clarification to the lane manager & lane committee.

Documentation of the Project

? Case study & documentation on completion of the scheme by ASB.
? Co-ordination between community & line agency.
? Users registration with line agency - monthly user billing.